"Power is probably the forever bottleneck": Grid delays threaten the AI race.

By Madison Mills
October 20, 2026  ·  Axios ↗
"Power is probably the forever bottleneck": Grid delays threaten the AI race.

Silicon Valley moves fast and breaks things, but the U.S. electrical grid moves slowly and requires permits.

Why it matters: Amid a wave of anxiety from Wall Street about the debt-fueled AI buildout, Goldman points to power as the biggest risk to trillions in spending in a new report shared exclusively with Axios.


Driving the news: Goldman expects global data center power demand to surge 170% between 2025 and 2030, with more than 60% of that growth coming from the U.S., according to the report.

Zoom in: The physical infrastructure needed to support AI is moving far more slowly than the technology itself.

Between the lines: The so-called AI race, which has long been defined by advances in frontier AI models, is really about who can get their hands on enough power, Goldman argues.

Follow the money: The massive expansion is being financed with debt, raising the stakes if construction timelines slip.

The intrigue: Since January, 86 projects have been canceled or significantly delayed, including 76 directly linked to local opposition, according to Goldman.

Yes, but: Slower deployment could also help prevent over-investment by giving actual demand time to catch up with spending.

Meanwhile: The boom is transforming utilities from traditionally slow-growing businesses into major beneficiaries of AI investment.

The bottom line: If you build AI systems, users will come, but they can only stay if there's enough power to go around.